The Rehabilitation of Hunter Road project is expected to begin on Sunday, April 21, and will consist of two phases. Both phases include repaving and milling Hunter Road from FM 306 to Gruene Road.
PHASE ONE: Phase one will begin with the Business District. This will include a full closure from Gruene Road to New Braunfels Street. Work will be from 10 p.m. to 9 a.m. and is expected to take only one night.
PHASE TWO: The second and last phase of the project will consist of only one lane closure and will be from New Braunfels Avenue to FM 306. Work will be from 7 p.m. – 7 a.m. and is expected to be complete on April 26, weather permitting.